Working form F12

Cash and Obligations Calendar

Identify the minimum balance, cash shortfall, expected receipts, and funds committed to obligations.

Supplementary startup guide

Use the startup guide to identify tool, transport, setup, and job-funding commitments. Enter their actual payment dates in your cash calendar rather than treating a tool subtotal as the whole startup budget.

Open the startup kit & launch budget →

Your cash calendar starts with unrestricted cash and no opening tax reserve. Show gross receipts, fees, bank payments, and the tax reserve separately. A reserve stays inside bank cash; remitting tax reduces the bank and releases only the reserve actually available.

Use the blank Your cash sheet in the formula planner for your own dates and delay scenarios. Project B below is fictional. With 800 USD starting cash its available-cash shortfall is 473.86 USD; without that 800 USD the required own float is 1273.86 USD, before a cushion.

Tax held must never fall below zero. A payment above the accumulated reserve still leaves the bank and uses unrestricted funds. Review the excess-payment warning in the planner: check the amount and project/period before relying on the funding plan. Later receipts do not automatically establish that an earlier payment was a tax credit. This worksheet is a planning tool, not a tax-liability ledger.

Blank and worked calculation sheets

Use the blank Your tabs for your own project. The Project B example tabs are separate.

Download formula planner ↓ · Open the complete teaching project →

Repeatable record

Use a separate record for each item. Copy this section in the editable workbook when you need additional rows.

Show a completed example
Project B event
Start
Gross receipt / fee USD
0 / 0
Bank outflow USD
0
Bank cash USD
800.00
Tax reserve / available cash USD
0 / 800.00
Project B event
Advance clears, day −5
Gross receipt / fee USD
1500 / 37.50
Bank outflow USD
0
Bank cash USD
2262.50
Tax reserve / available cash USD
136.36 / 2126.14
Project B event
Materials, day −4
Gross receipt / fee USD
0 / 0
Bank outflow USD
1750
Bank cash USD
512.50
Tax reserve / available cash USD
136.36 / 376.14
Project B event
Delivery, day −3
Gross receipt / fee USD
0 / 0
Bank outflow USD
190
Bank cash USD
322.50
Tax reserve / available cash USD
136.36 / 186.14
Project B event
Rental, day 1
Gross receipt / fee USD
0 / 0
Bank outflow USD
140
Bank cash USD
182.50
Tax reserve / available cash USD
136.36 / 46.14
Project B event
Fuel, day 1
Gross receipt / fee USD
0 / 0
Bank outflow USD
40
Bank cash USD
142.50
Tax reserve / available cash USD
136.36 / 6.14
Project B event
Help, day 2
Gross receipt / fee USD
0 / 0
Bank outflow USD
480
Bank cash USD
−337.50
Tax reserve / available cash USD
136.36 / −473.86; shortfall
Project B event
Final clears, day 3
Gross receipt / fee USD
4000 / 100
Bank outflow USD
0
Bank cash USD
3562.50
Tax reserve / available cash USD
500.00 / 3062.50; includes starting 800
Project B event
Tax remitted on actual due date
Gross receipt / fee USD
0 / 0
Bank outflow USD
500
Bank cash USD
3062.50
Tax reserve / available cash USD
0 / 3062.50; no second deduction from available cash

Related lessons

  • 05.2 — What to Buy, Rent, or Postpone
  • 06.2 — Build the Price and Check the Owner’s Earnings
  • 06.3 — Plan Payments and Cash Shortfalls
  • 06.4 — Work Through the Complete Practice Estimate
  • 07.2 — Test a Marketing Channel on a Small Budget
  • 08.2 — Agree on Payment Terms and Scope Changes

Typed answers stay in this browser. Export a copy for your own records. These educational forms are not official filings or a universal legal contract.