Working form F13

Estimate vs. Actual Results and Causes of Variances

Compare the same accepted scope and categories, separating change orders from overruns. Module 10 uses this same form.

Blank and worked calculation sheets

Use the blank Your tabs for your own project. The Project B example tabs are separate.

Download formula planner ↓ · Open the complete teaching project →

Repeatable record

Use a separate record for each item. Copy this section in the editable workbook when you need additional rows.

Show a completed example
Project B category
Price before sales tax
Plan
5000
Actual
5000
Variance
0
Cause / action
Scope did not change in this exercise
Project B category
Materials
Plan
1750
Actual
1850
Variance
+100
Cause / action
Investigate the cause; do not automatically attribute it to the market
Project B category
Help
Plan
480
Actual
560
Variance
+80
Cause / action
Check actual time and included work
Project B category
Delivery/hauling
Plan
190
Actual
190
Variance
0
Cause / action
Project B category
Rental
Plan
140
Actual
140
Variance
0
Cause / action
Project B category
Fuel
Plan
40
Actual
60
Variance
+20
Cause / action
Project B category
Processing fee, 2.5% of 5500
Plan
137.50
Actual
137.50
Variance
0
Cause / action
Same fictional price and processing terms
Project B category
Direct cash costs
Plan
2737.50
Actual
2937.50
Variance
+200
Cause / action
Includes processing fee once in each total
Project B category
Owner hours
Plan
30
Actual
36
Variance
+6
Cause / action
Confirm the cause
Project B category
Management labor value at 40 USD
Plan
1200
Actual
1440
Variance
+240
Cause / action
Fictional valuation; not a tax deduction
Project B category
Overhead
Plan
350
Actual
350
Variance
0
Cause / action
Same exercise allocation basis
Project B category
Remainder before allowance and other taxes
Plan
712.50
Actual
272.50
Variance
−440
Cause / action
200 additional costs + 240 owner labor value
Project B category
Planning allowance
Plan
150
Actual
Do not automatically treat as an actual expense
Variance
—
Cause / action
Do not deduct the allowance again along with the overrun it covered

Related lessons

  • 06.1 — Account for All Labor and Costs
  • 06.4 — Work Through the Complete Practice Estimate
  • 09.7 — Resolve an Unexpected Site Condition
  • 10.2 — Compare the Estimate with Actual Costs