Fence business · Lesson 09.3

Install the Posts for the Selected Design

Lesson outcome

Install and document posts under the selected verified specification, including protection and conditions for loading.

A conceptual pressure-treated wooden post passes through concrete whose crowned top projects above the adjacent grade. The crown is highest near the post and slopes outward on both sides; arrows show water directed away. No footing dimensions or structural design are specified. A separate inset records the author’s use of six-inch self-adhesive deck tape as additional wrap. The product brand, intended buried use, compatibility, and service life are not established; verify the selected product and its instructions. Wrap is additional protection, not a replacement for the raised drainage detail.
Lesson illustrationIn this detail, finish the footing slightly above grade and slope its top away from the post. Additional post protection records the creator’s reported 6 in deck-tape practice; verify the exact product and permitted use. Wrap does not replace drainage.
Open the full-size illustration ↗

Build the Specification Before Digging

A post transfers loads from the fence and gate to its footing. You cannot select it solely from the finished fence height or a salesperson's usual practice. In F18, collect the post material and cross section, suitability for ground contact, footing dimensions, selected concrete mix, site conditions, and permitted loading for the next stage. These parameters must come from the agreed design for this project and instructions for the products used. Clarify a missing specification before work instead of substituting a universal number from a video.

On this job, the author used eighteen pressure-treated posts in nominal four-by-four-inch size and reported a concrete embedment depth of two feet. These are details of the completed job. On a new job, select the cross section and footing for fence height, soil, wind exposure, gates, and applicable requirements. The words pressure treated do not establish suitability for ground contact: AWPA recommends checking the intended use on the labeling. At delivery, retain the label and verify the use category, fastener compatibility, and requirements for treating cut ends.

Distinguish standard fence posts from gate posts if the selected design calls for different parameters. Record which component each specification line covers. "All posts are the same" is acceptable only as a verified result for this project. Confirm exact dimensions and footing details for the actual design. If a parameter has not been established, leave it as an open specification item with a specific way to check it, rather than inserting a convenient assumption.

Prepare the Footings and Post Protection

After checking the fence location and utilities, organize safe access to each footing location. Before using equipment, establish the permitted excavation method and restrictions around utilities. If actual conditions change, stop work at the affected point and assess it separately. Water, unexpected soil, a large root, or an old footing can make the original design unsuitable. Enlarging the hole by eye or cutting an obstacle simply to preserve the schedule is not a justified design adjustment.

Check the dimensions and condition of the prepared footing before placing the post and covering it with soil or concrete. Show the measuring tool reading, post identifier, and recorded result. If the selected design requires a particular base preparation or another layer, verify its material and installation under that design. Do not automatically transfer steps from one manufacturer's demonstration to a mix and design they do not cover. The installation process must match the actual materials selected.

For additional protection, the author used a six-inch-wide roll of self-adhesive tape intended for deck components. He explains that most of the protection is below ground and that the photos show its upper edge. The brand and instructions have not yet been identified. The category "deck tape" does not establish suitability for prolonged contact with soil and concrete. Before demonstrating this method, check the specific product: permitted use, surface preparation, adhesion, and seams. The course describes the author's practice without promising an established service life.

Set and Hold the Required Position

Match each post's labeling with its drawing location, intended use, and orientation. Organize installation so the component stays under control until the footing can hold it independently. Check the line, elevation, and plumb with suitable tools, and use a safe method of temporary support. When working alone, plan to make these checks without trying to hold a heavy component while doing incompatible tasks. If that is not workable, change the way the operation is organized.

The author reports buying ordinary concrete at Home Depot and using two bags per post. For eighteen posts, that is thirty-six bags in his account. Bag weight, mix brand, and footing diameter were not provided, so bag count does not establish volume or a design to copy at any site. For your project, calculate the required volume from verified footing dimensions and the yield of the purchased product. Follow that product's instructions for water, preparation, and placement. A separate procedure for a QUIKRETE fast-setting product does not describe every bag of ordinary concrete.

On this job, the author began installing rails the day after setting the posts. Record that as the actual sequence rather than a waiting period for every mix. Permission to load the footing depends on the product, temperature, curing conditions, and selected design. Record the material, installation time, and conditions for proceeding to framing or a gate. A hard surface does not establish the required readiness. If conditions differ from the instructions or the waiting period is unclear, resolve that before loading.

Check the Posts Before Framing

After the required curing period, check the conditions that govern the next stage: post positions, gate openings, footing condition, and the ability to make the specified connections. Compare results with F18, rather than an attractive catalog photo. If a post moved, first establish the cause and an acceptable correction. Pulling it into position with the frame can conceal the deviation while leaving the problem. A footing correction or design change requires verification before assembly continues.

Complete the record of concealed stages. For a standard operation, a clear record is sufficient: post identifier, measurement before covering, selected material, and inspection result. Do not photograph a tool merely to increase the photo count; each image should answer a specific question. The Shoreline archive shows installed posts, footing surfaces, and the edge of the protection. Those images do not show excavation, concrete placement, or curing. On your own site, record those stages before they become inaccessible.

For the exercise, complete the specification and work through a situation where the actual footing does not match the selected design. Your response must identify the stopped operation, missing verification, person or source needed for the decision, and condition for resuming. Other safe tasks may continue if they are independent of the disputed area. The lesson's result is not a memorized depth; it is posts with a clear intended use, checkable installation, and a justified transition to the rest of the work.

Put it into practice

Your assignment

Prepare F18 for a fence post and a gate post; resolve a discovered footing discrepancy.

Inputs

Selected design

Post labeling

Concrete mix instructions

Instructions for the actual protective product

Actual measurements and site conditions

Your deliverable

Two checked post records, a concealed-work log, and a decision to correct or clarify the discrepancy.

Working forms: F17, F18, F19.

Notes are saved only in this browser. Keep a separate copy of important work and avoid entering customer personal information.

Show the worked solution
  • An unidentified protective product remains an open specification item; its application method is not guessed.
  • The loading condition is taken from the actual instructions and tied to installation conditions.
  • A deviation is not concealed by the frame; the affected post is rechecked.
Show the self-check criteria
  • Every value has a source
  • The wood's intended use is verified
  • Protection and footing are checked before covering
  • The loading condition is recorded

Sources: C-AWPA, C-QUIKRETE, A-OWNER-PROTECTION, PSE-LOCATE.