Follow a fictional 5,000-square-foot private-lawn order through remote agreement, full access and loading gates, battery equipment, clipping return, complete owner time, whole-pack stock, cash and an adverse weather branch. No physical job has been performed.
Follow the complete job
- 01 Survey and measured lawn
- 02 Scope and remote agreement
- 03 Equipment, batteries and compatibility
- 04 Clippings, litter and site finish
- 05 Safety, loading and stop decisions
- 06 Price and full owner value
- 07 Whole packs, stock and complete schedule
- 08 Acceptance, receipts and customer handoff
- 09 Adverse actual branch and variance
- 10 Chronological cash and customer tax
- 11 Launch, equipment choices and route sensitivity
- 12 Audit the case and prepare your own visit
01 Survey and measured lawn
Case L is an original fictional owner-operated lawn-care order. CASE OWNER and CASE CUSTOMER are invented identifiers. No customer, address, physical cut, photograph, permit, load test or paid job has occurred. This completed simulation illustrates a record, while real competence and site checks remain separate prerequisites.
The private parcel is 330 by 330 ft. Only F01, a 40 by 50 ft interior front lawn, and B01, a 50 by 60 ft interior back lawn, are included: 2,000 + 3,000 = 5,000 sq ft. Front and back are relative to the empty house, not a curbside suburban strip. The rest of the roughly 2.5-acre parcel is outside the purchased mowing service.
This teaching method fits only properties that can sustain its actual equipment, access, clipping and people/pet controls. Servicing 5,000 sq ft on this roughly 2.5-acre parcel is a deliberately narrow example, not a promise that a typical 5,000-sq-ft suburban lot will fit. The empty house is an additional Case L control because of its position inside the separation envelope; it is not a universal requirement that every mowing customer vacate a house. Before equipment commitment, screen several real candidate sites with permission and customer willingness, then check the complete route and owner time.
The mapped rectangles are F01 x 135–175/y 110–160 ft and B01 x 130–180/y 160–220 ft, sharing an edge without double-counting area. A 3-ft operator/trimmer movement margin gives an operating envelope x 127–183/y 107–223 ft. Its conservative 100-ft buffer stays within x 27–283/y 7–323 ft inside the parcel. Road, neighbor and uncontrolled public access are outside it. Distance is maintained from every operating position, including movement outside the turf edge. The house at x 240–275/y 145–185 ft is empty throughout powered work; CASE CUSTOMER and pets remain offsite until the tools are isolated. Staging near x 285/y 170 is tools-off. A fence does not reduce the distance. If one operator cannot observe and control the perimeter, the real status is HOLD.
Completed SIMULATED survey L-SUR-01 records healthy established tall fescue, dry firm near-level ground estimated 0–3 degrees, initial representative height 4.25 in, no hidden wire, glass, stones, animal waste, irrigation damage, slopes or soft patches in the accepted route. The 36-in clear gate is compared with an assumed measured 25-in mower outside width; a 21-in deck label is not an outside-width measurement. These are invented findings, not a substitute for walking and checking a real site.
| Area | Rectangle | Area | First / repeat net line |
|---|---|---|---|
| F01 | 40 × 50 ft | 2,000 sq ft | $64 / $48 |
| B01 | 50 × 60 ft | 3,000 sq ft | $96 / $72 |
References: LB01, LB03, LB18, LT02, LT04, LT06, LB06, LB07, LB20, LB10, LB11, LB02, LB05, LB13, LB17, LB04, LT12, LT09, LT10, LT11, LT16, LT17, LT18, LT19, LT22, LT23, LT20, LT07, CASE-L-01.
02 Scope and remote agreement
The customer initiates the remote inquiry on Day −7. Detailed photos, turf condition, dimensions, gate, exclusion plan, access and trailer position are confirmed remotely on Day −3. The complete offer and acceptance occur only by email on Day −2. There is no earlier in-person sales contact. First physical arrival is Day 0. The formation history is retained with L-FIRST-01; these invented dates are not proof of the rules applicable to another sale.
The accepted first offer is $160 net, with a hypothetical 10% customer tax of $16, totaling $176. The rate is arithmetic and is not asserted to be the current Vancouver or any local rate. Two agreed postcompletion payments of $88 clear on Day 0 and Day 1. No deposit, voluntary pre-work cancellation fee or voluntary rescheduling charge is imposed. Mandatory cancellation, notice, refund and remedy rights remain intact; remote acceptance is not a universal exemption.
Included work is the assessed test, supported mowing, grass trimming reachable from safe ground, fine clipping return to these healthy private lawns, ordinary safe litter collection, and controlled hard-surface finish. No grass haul or paid disposal is included. Exclusions are pesticide or fertilizer application, chemical treatment, disease diagnosis, tree or hedge work, ladders, public verges, hard edging, sod or repair, animal waste, needles, unknown contamination, removal of heavy wet windrows, and promises of weed-free or uniformly restored turf.
A new request is assessed and priced before work. CASE CUSTOMER requests no additions in the completed simulation. Unassessed planting beds and the rest of the parcel remain excluded. A real missed agreed strip requires review and an appropriate remedy; it is not automatically new billable scope. A conditional return visit at $120 net is a separate confirmed visit after fresh growth and safety checks, not an automatically renewed subscription.
References: LB01, LB03, LB18, LT02, LT04, LT06, LB02, LB04, LB16, LB17, LB19, LB05, LB06, LB07, LB08, LB09, LB14, LB20, LB10, LB11, LB12, LB13, LT12, LT07, LT10, LT17, LT18, LT22, LT11, CASE-L-01.
03 Equipment, batteries and compatibility
The selected teaching assembly is EGO LM2130SP mower in the LM2135SP kit, ST1520S trimmer, LB5300 blower, two BA4200T 7.5 Ah packs BAT01/BAT02, one BA1400T 2.5 Ah pack BAT03, and CH5500 charger. Match exact current manuals and accessories. Model names identify the case; they are not a recommendation that every learner purchase this equipment or proof that batteries last for the assumed workload.
Completed SIMULATED compatibility record L-COMP-01 selects mower height position 6, nominally 3 in, after isolated adjustment under the exact manual. Removing 1.25 in from 4.25 in is about 29.4%, within the one-third planning boundary. The final height, finish and clipping dispersion still need an observed small test. Dry, sound, healthy grass and a stable footing are assumed; a failed test, wetness, stress or unknown turf resets HOLD.
The trimmer has compatible 0.095-in twisted nylon line and begins with an assumed 13-ft head loading transferred from the purchased spool at the depot. That transfer is not consumption. The base plan has no onsite reload. First-visit net line use is assumed 7 ft, leaving 6 ft in the head and 227 ft on the spool, 233 ft in combined stock. Repeat use is another 4 ft. Real replenishment follows the exact current POWERLOAD sequence, including the prescribed battery states; a generic instruction to keep the battery removed throughout winding would be incomplete.
BAT01/BAT02/BAT03 and the charger are inspected for identity, condition, clean dry contacts and manual temperature limits. Charge only at the prepared dry indoor depot. Transport packs removed from tools, restrained separately against movement and short circuit in suitable protected dry containers. No loose battery, improvised charger, wet charging, vehicle heat exposure or customer outlet is assumed. Pack availability and a safe stopping plan must be physically demonstrated; up-to runtime advertising cannot validate this paper schedule.
Completed SIMULATED tests TF01 at F01 and TB01 at B01 each use a representative sound 3 by 10 ft test envelope containing one short centered pass; the full 30 sq ft is not claimed cut. TF01 is T + 35–39 and TB01 T + 40–44, with final stopped recording T + 44–45. Representative starting grass is 4.25 in, selected position 6 is nominally 3 in, and isolated after-test observations in the story are 3.0–3.2 in remaining, no fresh scalp, torn tips, rut or persistent clump. Fine clippings settle within the same private lawn. H01 at B01 southwest remains outside the cut test. No physical measurement has been performed.
The SIMULATED pack log assigns BAT01 to both tests and F01 mowing T + 45–63. At T + 63–64 the operator stops, waits for the blade, removes the pack and swaps on safe level ground before BAT02 powers B01 mowing through T + 90. BAT03 powers trimming T + 90–105, then is isolated and transferred to the compatible LB5300 for finishing T + 105–115. Packs start normal and fully charged only as a fictional condition. No exact remaining runtime, gauge prediction, charge time or demonstrated productive capacity is inferred.
SIMULATED ordinary line advance uses the already loaded ST1520S head as needed during its T90–105 trimming interval: with the correctly guarded head running, lightly tap the bump knob on a checked clean bare-ground/hard-soil point under the exact manual procedure. A firm debris-free tap point and stable stance inside the already assessed working envelope and 100-foot control are stipulated; no new public-side station is created. This is not a full reload. Failed advance requires stopping and battery removal for the instructed inspection/reload. No bump count, advance increment, runtime or extra elapsed time was measured. The existing seven-foot net-use assumption includes normal cutting/cut-off losses and is not calculated from taps.
| SIMULATED test | Elapsed minutes | Representative result |
|---|---|---|
| TF01 / F01 | T + 35–39 | 4.25 in before; 3.0–3.2 in remaining; no new visible scalp/rut/clump |
| TB01 / B01 | T + 40–44 | Same assumed test result; H01 remains outside test |
References: LB06, LB10, LB11, LB18, LT02, LT04, LT06, LT07, LT08, LT15, LT17, LT18, LT19, LT22, LB01, LB02, LB05, LB13, LB17, LB03, LB04, LT09, LT10, LT11, LT16, LT23, LT13, LT20, LT21, LT01, LT03, LT05, LT12, CASE-L-01.
04 Clippings, litter and site finish
Completed SIMULATED clipping record L-CLIP-01 returns fine healthy grass clippings to F01/B01 only where the test shows they disperse without smothering. The assumed dry moderate growth supports mulching. No green-waste load is exported and the modeled clipping-handling cash is explicitly $0. That verified-in-the-story zero is not permission to dump grass into an ordinary bin, road, drain, neighboring property or waterway.
CASE OWNER first removes ordinary safe loose paper and plastic litter, keeping the two rectangles separately recorded as two small bags. CASE CUSTOMER gives fictional prior permission BIN-L-01 for these ordinary-litter bags in the identified private ordinary-waste bin with spare capacity. The bags contain no grass, hazardous material, animal waste or sharps. Actual local acceptance and owner permission must both be checked; payment or a bin nearby does not establish an accepted route.
The blower has the applicable minimum separation, and the course uses the stricter 100-ft exclusion for every powered task. Use only the lowest controlled method that keeps material inside the agreed private receiving area; finish by rake/broom when that is safer. Never blow grit toward people, traffic, property, storm drains or through a boundary. Heavy clumps, unusual contamination or unavailable safe dispersion means stop and assess a different scope or lawful route.
Two disposable dry shop cloths are assumed consumed in the first exterior dry wipe/hand-tool finish and one in the return visit. No chemical wipe, solvent, pressurized water wash or wet charger cleaning is used. Follow the exact equipment cleaning instructions with the required isolation. The used ordinary nonhazardous dry cloths are contained within the existing ordinary-litter bags under the fictional BIN-L-01 acceptance; no extra bag or grass haul is charged. If real contamination or bin acceptance differs, stop and resolve that waste route. No laundering or arbitrary replacement of durable tools is charged as this consumable stock.
References: LB01, LB06, LB10, LB11, LB18, LT02, LT04, LT06, LT07, LT08, LT15, LT17, LT18, LT19, LT22, LB02, LB05, LB13, LB17, LB03, LB04, LT10, LT16, LT23, LT11, CASE-L-01.
05 Safety, loading and stop decisions
The exact mower and current trimmer instructions require at least 100 ft for people and pets; the blower minimum is 50 ft. The shared case control is at least 100 ft for all powered work. CASE OWNER checks the entire exclusion and access route before startup and continuously during use. Tools stop if a person or animal enters, visibility is lost, debris is thrown beyond control, footing deteriorates, a tool vibrates abnormally or a battery/tool condition changes.
The simulated PPE check uses side-protective eyewear, plus a face shield and fitted hearing protection for the selected trimmer/blower; the shield supplements the eyewear. Substantial footwear, long pants, appropriate fitted gloves, contained hair and no loose/dangling items match the L12 and Lesson 05.1 checks. All protective fit and inspections are fictional, not performed tests.
The already owned tow vehicle and compliant trailer are separately funded and assumed suitable for the complete restrained load. The teaching trailer has a 12-in bed height and prepared compatible WR06 supports. An EZ-ACCESS TRAVERSE WR06 full-width ramp provides a continuous 30.5-in usable operator/cargo surface, uses both clevis pins and the underside strap, and requires both supports to meet its 1,200-lb rating. The 49-lb ramp and assumed 55.3-lb isolated mower are not personal handling limits. Actual ramp deployment/retrieval, anchor compatibility, ground contact, securement, footwear, stopping and safe solo rolling remain unverified; difficulty requires HOLD or a revised staffing/equipment plan.
Unload and load the isolated mower with batteries removed on the prepared dry supported full-width route. No operator jumps a gap, carries an assembled mower onto a tall bed, uses an unsecured board or infers an allowable angle from overall ramp length. The actual operator-plus-cargo load and every support condition must meet the exact ramp manual. Secure the mower, other tools, ramp and separately protected packs before road movement, and recheck legal tow/trailer ratings and restraint requirements.
Completed SIMULATED stop record HOLD-L-01 belongs only to the adverse actual branch: on Day 0, customer-supplied predeparture images and the owner weather review indicate wet turf. CASE OWNER does not travel to cut it and agrees a new Day 2 check without a penalty. The Day 2 fictional recheck is dry/firm with representative 4.4-in grass; a nominal 3-in cut removes about 31.8%, still below one third. No model directs mowing wet grass to rescue a margin. No injury, release or equipment defect is entered in this simulated file.
References: LB06, LB10, LB11, LB18, LT02, LT04, LT06, LT07, LT08, LT15, LT17, LT18, LT19, LT22, LB05, LB01, LB02, LB13, LB17, LB03, LB04, LT12, LT10, LT16, LT23, LT11, LT20, LT13, LT21, LT14, LT24, LT01, LT03, LT05, LT09, CASE-L-01.
06 Price and full owner value
The $160 first price is an invented accepted task price, split $64 F01 and $96 B01. It is not a market survey or a national square-foot rate. Its $176 gross is paid as two $88 receipts, each with an assumed 2.5% plus $0.30 processing fee: $2.50 each, $5 total. Tax collected is not another $16 of service revenue. Record each actual fee even when a real payment method charges zero.
Planned direct cost is $2.13 stock + $8 transport fuel + $0.30 depot charging + $0 clipping-haul cost + $5 fees = $15.43. Full-cycle owner time is 3.5 hours at an assumed $25 = $87.50, plus $12 reusable equipment and $9 overhead allocation. The management result is $160 − $15.43 − $87.50 − $12 − $9 = $36.07 before allowance and other business taxes; after a separate $10 planning allowance it is $26.07. Valuing unpaid owner time does not itself create payroll or a bank payment.
The $0.30 electricity cost uses an invented 1.20 kWh of allocated depot AC recharge at a hypothetical $0.25/kWh owner reimbursement. Repeat uses 1.00 kWh/$0.25. These are neither measured energy nor a tariff or a battery-runtime claim. The cash record assumes this small recorded reimbursement is paid on Day −1, separate from the full equipment purchase and battery replacement allocation.
Including the $10 allowance, nonfee cost is $118.93 and two fixed fee components total $0.60. Algebra gives ($118.93 + $10 + $0.60)/(1 − 0.025 × 1.10) = about $133.1928; a conservative cent ceiling is $133.20. Tax $13.32 makes gross $146.52, two $73.26 payments each cost $2.13, and the result after allowance is $0.01. Recheck the separately rounded fees. This covers assumed costs only; it does not establish a suitable, lawful or competitive offer.
| Line | First plan | Same-customer return |
|---|---|---|
| Net service | $160.00 | $120.00 |
| Customer tax, hypothetical | $16.00 | $12.00 |
| Stock use | $2.13 | $1.10 |
| Fuel / depot energy | $8.00 / $0.30 | $6.00 / $0.25 |
| Rounded receipt fees | $5.00 | $3.60 |
| Owner time value | $87.50 | $62.50 |
| Equipment / overhead | $12.00 / $9.00 | $12.00 / $9.00 |
| Result before allowance | $36.07 | $25.55 |
| Allowance / result after | $10.00 / $26.07 | $8.00 / $17.55 |
References: LB05, LB06, LB07, LB08, LB09, LB14, LB20, LB01, LB02, LB17, LB10, LB11, LB13, LB03, LB04, LB18, LT01, LT02, LT03, LT04, LT05, LT06, LT07, LT08, LT16, LT17, LT18, LT19, CASE-L-01.
07 Whole packs, stock and complete schedule
Day −1 purchases are one 240-ft compatible line spool for $18, one 20-count ordinary-litter bag pack for $12 and one 40-count dry cloth pack for $8: $38 cash. All are fictional landed all-in allowances, with actual purchase-tax treatment left for the learner to research.
First use is 7 ft of line at the full-precision $18/240 = $0.075 basis, posted as $0.53; two bags cost $1.20 and two cloths $0.40. Total posted issue is $2.13 and stock closes at $38 − $2.13 = $35.87. Line closes at 233 ft and $18 − $0.53 = $17.47. Do not round the unit rate to $0.08 or recompute the carried value as $17.48. The 13-ft head loading remains a transfer within combined head/spool inventory.
The next visit opens with the recorded 233 ft/$17.47. Its full-precision line basis is $17.47/233, not a new rounded rate. Four feet post $0.30, one bag $0.60 and one cloth $0.20, totaling $1.10; stock closes $34.77. Future purchases at a different price blend actual opening quantity and carrying value with the complete new package. The final depletion absorbs the residual cent rather than inventing or losing inventory.
The first full cycle is 210 minutes: 135 onsite, 20 depot preparation, 30 round-trip transport and 25 remote assessment/quote/records. Onsite T + 0–20 covers arrival/unload/setup, + 20–35 litter/access, + 35–45 test, + 45–90 mowing, + 90–105 trimming, + 105–115 finish and + 115–135 inspection/handoff/reload. The clock is a fictional planning allowance, not demonstrated productivity. Manual work, battery changes, pauses and safe stop decisions must fit or the plan must change.
The same-customer return is separately assessed around Day 7. Its 150-minute full cycle has 90 onsite, 15 prep, 30 travel and 15 admin. A shorter return assumes the original records remain applicable and growth/test conditions support it. Rain, dormancy, leaf load, holidays, customer absence and seasonal growth change the date or scope. No weekly work or income is guaranteed.
| Owner task | First min | Return min | Adverse actual min |
|---|---|---|---|
| Remote assessment, quote, weather review and records | 25 | 15 | 40 |
| Depot inspection, dry charging preparation and loading | 20 | 15 | 30 |
| Round-trip transport | 30 | 30 | 50 |
| Arrival, unloading, access control and ordinary litter | 35 | 25 | 35 |
| Test, mowing and trimming | 70 | 45 | 70 |
| Clipping dispersion and hard-surface finish | 10 | 5 | 10 |
| Inspection, customer handoff and isolated reload | 20 | 15 | 20 |
| First onsite task | Elapsed min |
|---|---|
| Arrival, isolation check, unload and setup | T + 0–20 |
| Litter and exclusion control check | T + 20–35 |
| Inconspicuous cut/dispersion test | T + 35–45 |
| Mowing both assessed rectangles | T + 45–90 |
| Supported grass trimming | T + 90–105 |
| Manual/controlled finish and clipping dispersion | T + 105–115 |
| Final check, customer return after isolation, handoff and reload | T + 115–135 |
References: LB01, LB02, LB05, LB17, LB06, LB09, LB20, LB07, LB10, LB11, LB18, LT02, LT04, LT06, LT07, LT08, LT15, LT17, LT18, LT19, LT22, LB13, LB03, LB04, LT09, LT10, LT11, LT16, LT23, LT12, LT20, LT13, LT21, LT14, LT24, LT01, LT03, LT05, CASE-L-01.
08 Acceptance, receipts and customer handoff
Completed SIMULATED handoff L-HAND-01 occurs after isolation near T + 125 within the final 20-minute stage. CASE CUSTOMER returns only after CASE OWNER confirms all powered tools are stopped, batteries removed as prescribed and the route safe. From ordinary safe positions they compare F01/B01 with the accepted test and scope. No real photograph, customer, signature or physical inspection is claimed.
The fictional result records ordinary growth cut to the supported nominal setting, reachable grass trimming completed, no new visible rut or scalp entered, fine clippings dispersed on the included healthy grass, two ordinary-litter bags accepted under BIN-L-01 and no grass exported. Preexisting thin patch H01 at B01 southwest remains as disclosed; overseeding, disease treatment and a uniformly dense lawn were excluded. Loose windrows, escaped litter or a missed agreed strip would require correction/review rather than a perfect-result statement.
The invoice is $160 net + $16 illustrative tax = $176. RCP-L-01 $88 clears Day 0 with its $2.50 fee; $8 tax is held. The second $88 is still receivable at this snapshot. Project bank is $185.50, held tax $8 and free cash $177.50. On Day 1 RCP-L-02 clears with another $2.50 fee, leaving zero invoice balance, $271 bank, $16 held tax and $255 free cash. Pending payments never enter bank as cleared cash.
Completed SIMULATED next-visit action A-L-01 records a proposed Day 7 check, conditional on actual growth, dryness, access and exclusion control. No automatic renewal or fixed weather guarantee is promised. A real complaint is documented and assessed against the agreed scope and mandatory remedies. No testimonial, review request or external message has been fabricated or sent.
References: LB10, LB11, LB01, LB06, LB09, LB07, LB20, LB18, LT02, LT04, LT06, LT07, LT08, LT15, LT17, LT18, LT19, LT22, LB05, LT13, LT20, LT21, LT12, LT14, LT24, CASE-L-01.
09 Adverse actual branch and variance
The adverse actual is an alternative outcome of the same accepted L-FIRST-01 scope, not another customer or the repeat visit. Day 0 predeparture wetness HOLD avoids a wasted onsite attempt; the visit completes only after the fictional Day 2 dry/firm 4.4-in recheck. Extra weather administration is 15 minutes, depot preparation 10 minutes and transport 20 minutes, raising full owner time from 210 to 255 minutes, 4.25 hours at $25 = $106.25. This is not a claim of two identical $8 trips.
Actual fuel is recorded as $12 instead of $8. Depot energy stays $0.30; no extra runtime is invented from the delay. Normal stock use remains $2.13. A documented jam/waste during isolated depot preparation loses 8 additional feet of line ($0.60), one damaged bag ($0.60) and one extra unusable cloth ($0.20), total $1.40 assigned to this job. No extra pack is bought; stock closes $38 − $2.13 − $1.40 = $34.47. These losses are not additional cash purchases.
Actual direct cost is $3.53 total job stock + $12 fuel + $0.30 energy + $5 fees = $20.83. Result is $160 − $20.83 − $106.25 − $12 − $9 = $11.92. Compared with the static accepted $36.07 before allowance it is $24.15 worse: $1.40 stock loss + $4 fuel + $18.75 owner value. The $10 planning allowance is not deducted again as an actual bill. Compared with $26.07 after allowance, the actual shortfall is $14.15.
RCP-L-A01/A02 clear on Day 2 and Day 3, each $88 and $2.50 fee. The actual pre-receipt cash outflow is $38 + $0.30 + $12 = $50.30, leaving a $96 low point from $146.30. A separate $4 real owner contribution would restore the chosen $100 cushion without service revenue or customer tax. The unfunded actual branch ends $267 bank, $16 held tax and $251 free cash. Its cash timing is not silently copied onto the dry base Day 0/1 calendar.
The actual worksheet keeps Plan values as retained accepted values and ID/date, rather than links to a changing estimate. Investigate line preparation, route planning and weather communication. Changing a future price cannot rewrite this historical comparison or justify overriding a safe stop.
| Metric | Static plan | Actual | Actual less plan |
|---|---|---|---|
| Full owner hours | 3.50 | 4.25 | 0.75 |
| Job stock | $2.13 | $3.53 | $1.40 |
| Fuel | $8.00 | $12.00 | $4.00 |
| Owner value | $87.50 | $106.25 | $18.75 |
| Result before allowance | $36.07 | $11.92 | −$24.15 |
References: LB01, LB06, LB09, LB07, LB20, LB10, LB11, LB05, LT02, LT04, LT06, LT10, LT11, LT22, CASE-L-01.
10 Chronological cash and customer tax
Opening project bank is $146.30 including an explicit $0 held tax. It comprises one chosen $100 free-cash cushion and a $46.30 bridge for $38 whole-package stock, $0.30 depot energy and $8 fuel. The cushion is a retained target, not an expense or another profit deduction. Equipment acquisition, setup and first-month overhead are funded outside this isolated calendar.
Enter consecutive dated rows: Day −1 stock $38, Day −1 depot energy reimbursement $0.30, Day 0 fuel $8, Day 0 gross receipt $88 with $2.50 fee, Day 1 second gross $88 with $2.50 fee. All other amounts on each row are explicitly zero when known. Minimum free cash is $100; ending bank is $146.30 − $46.30 + $176 − $5 = $271. The $16 reserve is inside that bank, leaving $255 unrestricted.
Repeat cash carries both $271 bank and $16 held tax from the dry planned branch. On nominal Day 7, it pays $6 fuel and $0.25 depot energy before $132 clears with its $3.60 fee. Ending bank is $393.15, held tax $28 and free cash $365.15. No stock pack is bought, although $1.10 stock is consumed. Add actual intervening tax, overhead, withdrawals and other visits before interpreting this as a company balance.
Customer gross goes in D, actual withheld fee in E, other cash paid in F, tax remitted in H and verified noncustomer funding in O. Every active row requires all five numeric amounts and a numeric chronological day/date. A blank fee is unknown; zero is a checked zero. A fee withheld in E is not charged again in F. Owner funding in O increases bank without creating customer tax or service revenue.
Tax remittance leaves the bank in full. The reserve clamps at zero and excess-remittance warnings remain after later receipts. This reconciles modeled cash; it does not establish a tax refund, credit or actual liability. Reconcile actual registration, classification, location, rates and returns separately. Neither held customer tax nor an opening owner contribution is job profit.
| Day | Cash event | Gross in | Fee | Other paid |
|---|---|---|---|---|
| −1 | Whole packs | $0 | $0 | $38.00 |
| −1 | Depot charge reimbursement | $0 | $0 | $0.30 |
| 0 | Transport fuel | $0 | $0 | $8.00 |
| 0 | Postcompletion receipt 1 | $88.00 | $2.50 | $0 |
| 1 | Postcompletion receipt 2 | $88.00 | $2.50 | $0 |
References: LB05, LB06, LB07, LB08, LB09, LB14, LB20, LB01, LB10, LB11, LB18, LT02, LT04, LT06, LT07, LT08, LT15, LT17, LT18, LT19, LT22, LB02, LB13, LB17, LB03, LB04, CASE-L-01.
11 Launch, equipment choices and route sensitivity
The fictional matched owned kit is $2,400, including both 7.5 Ah packs, the 2.5 Ah pack and charger, PPE/site controls, WR06 ramp with the required attachment/securement items and hand tools. It is a landed planning allowance, not verified supplier pricing. The $12 management allocation is $2,400/200 modeled visits, and $9 overhead is $360/40 modeled visits. Those denominators do not create customers, battery life or demand.
Business launch cash is $2,400 equipment + $180 setup + $360 first-month overhead + one $100 cushion + $46.30 first bridge = $3,086.30. A household with invented $2,800 monthly needs choosing three months of runway separately needs $8,400, for $11,486.30 combined. Booked future visits and gross receipts do not prove that amount can be withdrawn safely.
Already owned compliant towing transport is funded separately. A separate fictional $4,000 trailer acquisition raises business launch cash to $7,086.30 before any tow-vehicle acquisition, taxes, registration, insurance, finance or maintenance. Existing owned equipment still needs maintenance and replacement funding. For a narrow rental comparison, replacing $12 ownership allocation with a fictional $90 matched rental changes first result to $36.07 + $12 − $90 = −$41.93 before allowance, or −$51.93 after $10. Cash adds the full $90 to the $46.30 bridge, making $136.30, or $236.30 opening with the chosen $100 cushion; the noncash $12 was never a bank outflow. Actual matched batteries, charger, ramp/securement, pickup/return, charging, deposits, transport and terms need their own supported plan.
The $120 return price belongs to this same assessed customer and conditional route. For a different new customer, an extra 45 minutes of assessment/transport at $25 plus $4 fuel reduces the first-price result by $22.75 to $13.32 before allowance/$3.32 after. Applying the return price to that different-customer burden reduces $25.55 to $2.80 before its $8 allowance, or −$5.20 after. Equal square feet do not justify the same price or repeated demand.
Rain holds, dormant periods, seasonal growth, charger or tool failure and customer access change capacity. Build low-demand months with fewer completed paid visits and retain safe cancellation/rescheduling terms. Do not multiply a good dry-day result into an annual income promise. If the paper time or battery/handling plan fails in practice, revise the plan rather than forcing the original margin.
| Owned-kit item | Fictional landed budget |
|---|---|
| LM2135SP mower kit: LM2130SP, BA4200T 7.5 Ah BAT01 and CH5500 | $850.00 |
| ST1520S trimmer | $250.00 |
| LB5300 blower | $180.00 |
| BA4200T 7.5 Ah spare BAT02 | $320.00 |
| BA1400T 2.5 Ah BAT03 | $200.00 |
| PPE and private-site exclusion controls | $100.00 |
| WR06 ramp, both pins, underside strap, prepared anchors and cargo restraints | $400.00 |
| Hand tools and manual finish equipment | $100.00 |
References: LB02, LB03, LB04, LB16, LB17, LB19, LB01, LB05, LB06, LB09, LB07, LB20, LB12, LB13, LB10, LB11, LB18, LT01, LT02, LT03, LT04, LT05, LT06, LT07, LT08, LT16, LT17, LT18, LT19, CASE-L-01.
12 Audit the case and prepare your own visit
Audit area: 2,000 + 3,000 = 5,000 sq ft inside a much larger parcel with the complete exclusion envelope. Audit first owner time: 135 onsite + 20 prep + 30 travel + 25 admin = 210 minutes/3.5 hours. Repeat totals 150 minutes/2.5 hours, while the adverse branch totals 255 minutes/4.25 hours. None is a measured production rate.
Audit stock: $38 purchase − $2.13 first issue = $35.87; minus $1.10 return issue = $34.77. The alternative actual instead closes at $34.47 after $1.40 job losses. Combined line stock includes what remains on the head. Carry the posted $17.47 line value and 233 feet, not a recomputed rounded rate. Audit both separate $2.50 receipt fees and the one $3.60 return fee.
Study First plan, First cash, First actual, Repeat plan and Repeat cash in the nine-tab workbook. Your estimate, Your cash and Your actual remain neutral blank own-job forms. Preserve a dated accepted file and paste values into the actual Plan baseline. Formula protection helps against accidental edits; it is not security or a substitute for backups. The file is checked by the bundled calculation engine and saved-file reimport, not a native Excel application test.
Your completed local readiness packet needs actual site geometry, access/exclusion control, exact equipment/manual compatibility, safe full loading and battery cycle, lawful clipping/litter routes, formation/cancellation research, itemized costs, actual cash dates and customer acceptance. Each unresolved physical or legal prerequisite remains HOLD. A filled simulated record supplies an example; it does not authorize operation at a real home.
References: LB01, LB03, LB18, LT02, LT04, LT06, LB02, LB04, LB16, LB17, LB19, LB05, LB06, LB07, LB08, LB09, LB14, LB20, LB10, LB11, LB12, LB13, LT12, LT13, LT14, LT24, LT07, LT08, LT16, LT17, LT18, CASE-L-01.
Prepare your own job
Replace fictional site observations, approval assumptions, tax, prices, time and costs with evidence for your actual job. Use L20 and L22 and the blank Your estimate, Your cash and Your actual sheets. Preserve a dated accepted baseline.
- Course programWord document · American English
- Complete written courseWord document · American English
- Workbook and worked answersWord document · American English
- Complete Case L job guideWord document · American English
- Formula plannerExcel workbook · American English
- Optional WMP business referenceWord reference · American English